| Project No. | 172 |
| Wing | North Wing |
| Division | Road Division Muzaffarpur -2 |
| Circle | North Bihar Road Circle Muzaffarpur |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹26.89 Cr |
| Sanctioned Length | 12.74 km |
| Contractor | MAHESH KUMAR SINGH |
| AA Date | 21-12-2016 |
| Start Date | 06-11-2019 |
| Expected Completion | 31-03-2023 |
Road work completed. Signage Work in Progress. EOT granted up to 20.08.2022
Superintending Engineer quality visit record
North Bihar Road Circle Muzaffarpur · Road Division Muzaffarpur -2
Visited: 15 Jul 2024"Jungle Clearance required,"