MDRRCD BiharCompleted
Widening and Strengthening work from (Single Lane to Intermediate Lane) of Barahi (SH-87) to Dimahi PWD Road via Sahasram, Dharharwa, Sirsiya Village in Km (0+000 to 11+250)
#163
Road Division Sitamarhi.
North Bihar Road Circle Muzaffarpur
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹22.94 Cr
Length11.25 km
Start16-06-2020
Completion15-09-2021
MDR · North Wing
Road Division Sitamarhi.
M/s Kabbu Khirhar
Project Details
6 FieldsProject No.
163
Wing
North Wing
Division
Road Division Sitamarhi.
Circle
North Bihar Road Circle Muzaffarpur
Road Type
MDR
Head
State Plan
Cost & Timeline
6 FieldsAgreement Value
₹22.94 Cr
Sanctioned Length
11.25 km
Contractor
M/s Kabbu Khirhar
AA Date
14-10-2019
Start Date
16-06-2020
Expected Completion
15-09-2021
Widening and Strengthening work from (Single Lane to Intermediate Lane) of Barahi (SH-87) to Dimahi PWD Road via Sahasram, Dharharwa, Sirsiya Village in Km (0+000 to 11+250) is a Bihar Road Construction Department (RCD) project under Road Division Sitamarhi., classified as a MDR. The agreement amount for this project is ₹22.94 Cr, and the current status is Completed.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
Work Completed and CD 9 No. Completed (CD Target not visible in this application)
?
Frequently Asked Questions
- QWhat is the current status of the Bihar RCD project "Widening and Strengthening work from (Single Lane to Intermediate Lane) of Barah"?
- Status: Completed. This MDR project under Road Division Sitamarhi. (North Bihar Road Circle Muzaffarpur) covers 11.25 km of road work. Expected completion: 15-09-2021.
- QWho is the contractor for RCD project 163?
- The contractor for this project is M/s Kabbu Khirhar. Project number: 163. Division: Road Division Sitamarhi.. Administrative approval date: 14-10-2019.
- QWhat is the agreement value for this Bihar road project?
- The agreement value for "Widening and Strengthening work from (Single Lane to Interme" is ₹22.94 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Sitamarhi..
- QWhat does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 163 "Widening and Strengthening work from (Single Lane to Interme" is one of thousands of road improvement and construction works tracked by BiharInfraTales.