MDRRCD BiharCompleted
Widening & Strengthening work in Km. 0.00 to 41.715 (Total length 41.715 km) of Mairwan Kuchaikot Road including Construction of RCC Drains & 3Nos H.L. Bridges
#146
Road Division Gopalganj
Saran Road Circle Hajipur.
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹79.88 Cr
Length41.72 km
Start20-11-2018
Completion31-12-2022
MDR · North Wing
Road Division Gopalganj
Sona Engicon Pvt. Ltd.
Project Details
6 FieldsProject No.
146
Wing
North Wing
Division
Road Division Gopalganj
Circle
Saran Road Circle Hajipur.
Road Type
MDR
Head
State Plan
Cost & Timeline
6 FieldsAgreement Value
₹79.88 Cr
Sanctioned Length
41.72 km
Contractor
Sona Engicon Pvt. Ltd.
AA Date
24-11-2017
Start Date
20-11-2018
Expected Completion
31-12-2022
Widening & Strengthening work in Km. 0.00 to 41.715 (Total length 41.715 km) of Mairwan Kuchaikot Road including Construction of RCC Drains & 3Nos H.L. Bridges is a Bihar Road Construction Department (RCD) project under Road Division Gopalganj, classified as a MDR. The agreement amount for this project is ₹79.88 Cr, and the current status is Completed.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
Work completed boulder pitching work is in progress at HL bridge
?
Frequently Asked Questions
- QWhat is the current status of the Bihar RCD project "Widening & Strengthening work in Km. 0.00 to 41.715 (Total length 41.715 km) of "?
- Status: Completed. This MDR project under Road Division Gopalganj (Saran Road Circle Hajipur.) covers 41.72 km of road work. Expected completion: 31-12-2022.
- QWho is the contractor for RCD project 146?
- The contractor for this project is Sona Engicon Pvt. Ltd.. Project number: 146. Division: Road Division Gopalganj. Administrative approval date: 24-11-2017.
- QWhat is the agreement value for this Bihar road project?
- The agreement value for "Widening & Strengthening work in Km. 0.00 to 41.715 (Total l" is ₹79.88 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Gopalganj.
- QWhat does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 146 "Widening & Strengthening work in Km. 0.00 to 41.715 (Total l" is one of thousands of road improvement and construction works tracked by BiharInfraTales.