| Project No. | 1223 |
| Wing | North Wing |
| Division | Road Division Sitamarhi. |
| Circle | North Bihar Road Circle Muzaffarpur |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹5.91 Cr |
| Sanctioned Length | 3.00 km |
| Contractor | AMAR ENGICON AND CONSTRUCTION PRIVATE LIMITED |
| AA Date | 04-07-2025 |
| Start Date | 03-02-2026 |
| Expected Completion | 02-02-2027 |
Work is progress. There is an issue of Tree cutting and tree translocation in the alignment of Majorganj-Dheng Drain. from letter no.-1334 dt. 29.04.2026 of this office cordinated with forest officer, Sitamarhi forest Division for providing Estimate of Tree translocation and Tree cutting.
Superintending Engineer quality visit record
North Bihar Road Circle Muzaffarpur · Road Division Sitamarhi.
Visited: 18 Apr 2026"For the construction of Drain E/W PCC & Rebar tying was in progress. The construction work was instructed to be carried out from end of ROW of road as per specification."