Bihar RCD PMIS — Road Project◐ Ongoning
Agreement₹42.21 Cr
Length14.00 km
Start18-06-2026
Completion05-01-2028
MDR · Simanchal Wing
Road Division Katihar.
TOPLINE INFRA PROJECTS PRIVATE LIMITED
Project Details
6 FieldsProject No.
1186
Wing
Simanchal Wing
Division
Road Division Katihar.
Circle
Road Circle Purnea
Road Type
MDR
Head
State Plan
Cost & Timeline
6 FieldsAgreement Value
₹42.21 Cr
Sanctioned Length
14.00 km
Contractor
TOPLINE INFRA PROJECTS PRIVATE LIMITED
AA Date
17-07-2025
Start Date
18-06-2026
Expected Completion
05-01-2028
Widening & Strenghening for Old alignment of Purnea-Katihar Road (NH-131A) from (i) Lelha Chowk to IOCL Petrol Pmup Ch (62.11 To 63.011) KM & (ii) Dalan Chowk to Kushwaha Chowk Ch (47.35 To 60.45) KM. Total Length-14.00 KM for the Year 2025-2026 is a Bihar Road Construction Department (RCD) project under Road Division Katihar., classified as a MDR. The agreement amount for this project is ₹42.21 Cr, and the current status is Ongoning.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
Work in Progress..
?
Frequently Asked Questions
- QWhat is the current status of the Bihar RCD project "Widening & Strenghening for Old alignment of Purnea-Katihar Road (NH-131A) from "?
- Status: Ongoning. This MDR project under Road Division Katihar. (Road Circle Purnea) covers 14.00 km of road work. Expected completion: 05-01-2028.
- QWho is the contractor for RCD project 1186?
- The contractor for this project is TOPLINE INFRA PROJECTS PRIVATE LIMITED. Project number: 1186. Division: Road Division Katihar.. Administrative approval date: 17-07-2025.
- QWhat is the agreement value for this Bihar road project?
- The agreement value for "Widening & Strenghening for Old alignment of Purnea-Katihar " is ₹42.21 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Katihar..
- QWhat does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 1186 "Widening & Strenghening for Old alignment of Purnea-Katihar " is one of thousands of road improvement and construction works tracked by BiharInfraTales.