East Central RailwayIn Progress

Construction of Type-II, Type-III, Type-IV Quarters, RCC tanks, FOB, RUB extension of minor bridges, approach road, development of circulating area and other miscellaneous works at different stations from Ghoswar Station (Km 5.50) to Harsidhi Bazar station (km 136.863) in connection with HJP-SGL New Rail Line Project

Estimate Cost

₹56.73 Cr

Sanctioned estimate

Tendered Cost

₹70.87 Cr

+24.9% vs estimate

Physical Progress

92%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹70.87 Cr
Progress92%
Started27-09-2018
Target DOC31-07-2026
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP

Work Details

5 Fields
Work No.
272
Agency
Hari Construction and Associates Private Limited
Keshawe, Barauni, Begusarai, Bihar
Acceptance / LOA
ECR/CAO/Con/WT/Agt/29 Dated 08.01.2019
Officer in Charge
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹56.73 Cr
Tendered Cost
₹70.87 Cr
Physical Progress
92%
Date Started
27-09-2018
Original DOC
16-03-2020
Extended DOC
31-07-2026

Construction of Type-II, Type-III, Type-IV Quarters, RCC tanks, FOB, RUB extension of minor bridges, approach road, development of circulating area and other miscellaneous works at different stations from Ghoswar Station (Km 5.50) to Harsidhi Bazar station (km 136.863) in connection with HJP-SGL New Rail Line Project is an East Central Railway (ECR) infrastructure work in Bihar, executed by Hari Construction and Associates Private Limited. The tendered cost of the work is ₹70.87 Cr, and it is currently In Progress with physical progress recorded at 92%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

tendered_cost_crore raw: 70.87 after 3rd variation value 88.31

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of Type-II, Type-III, Type-IV Quarters, RCC tanks, FOB, RUB extensi"?
Status: In Progress. This East Central Railway work is being executed by Hari Construction and Associates Private Limited. Physical progress stands at 92%. Current date of completion (DOC): 31-07-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is Hari Construction and Associates Private Limited, Keshawe, Barauni, Begusarai, Bihar. Acceptance / agreement reference: ECR/CAO/Con/WT/Agt/29 Dated 08.01.2019. Work started on 27-09-2018.
QWhat is the cost of this railway work?
The tendered cost of "Construction of Type-II, Type-III, Type-IV Quarters, RCC tan" is ₹70.87 Cr (against an estimate of ₹56.73 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of Type-II, Type-III, Type-IV Quarters, RCC tan" is one of hundreds of railway works covered.