East Central RailwayIn Progress

Tender No. ECR-CAO-C-N-ETN-54-20-21 closing date 04-02-2021 for Manufacturing, fabrication, Installation of glued insulated joint 60 Kg/52 Kg (In situ) between Sagauli (incl.)-NKE (Excl) section for doubling project Sagauli-NKE under jurisdiction of Dy.CE/Con/BTH.

Estimate Cost

₹1.41 Cr

Sanctioned estimate

Tendered Cost

₹1.68 Cr

+19.1% vs estimate

Physical Progress

98%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹1.68 Cr
Progress98%
Started05-12-2021
Target DOC31-12-2026
Sri Indrajit Kumar, CE/C/NW; Sri Ajay Kumar, Dy.CE/C/BTH; Sri Nirmal Shalhata, AEN/Con/II/BTH

Work Details

5 Fields
Work No.
308
Agency
Acceptance / LOA
ECR-CAO-C-N-ETN-54-20-21 dated. 23/03/2021
Officer in Charge
Sri Indrajit Kumar, CE/C/NW; Sri Ajay Kumar, Dy.CE/C/BTH; Sri Nirmal Shalhata, AEN/Con/II/BTH
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹1.41 Cr
Tendered Cost
₹1.68 Cr
Physical Progress
98%
Date Started
05-12-2021
Original DOC
22-09-2021
Extended DOC
31-12-2026

Tender No. ECR-CAO-C-N-ETN-54-20-21 closing date 04-02-2021 for Manufacturing, fabrication, Installation of glued insulated joint 60 Kg/52 Kg (In situ) between Sagauli (incl.)-NKE (Excl) section for doubling project Sagauli-NKE under jurisdiction of Dy.CE/Con/BTH. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/S Arvind Industries-Kolkata. The tendered cost of the work is ₹1.68 Cr, and it is currently In Progress with physical progress recorded at 98%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Tender No. ECR-CAO-C-N-ETN-54-20-21 closing date 04-02-2021 for Manufacturing, f"?
Status: In Progress. This East Central Railway work is being executed by M/S Arvind Industries-Kolkata. Physical progress stands at 98%. Current date of completion (DOC): 31-12-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/S Arvind Industries-Kolkata, Stephen House, 4 B B D Bag East, Room No 51c, 3rd Floor, Kolkata-700001, West Bengal, India. Acceptance / agreement reference: ECR-CAO-C-N-ETN-54-20-21 dated. 23/03/2021. Work started on 05-12-2021.
QWhat is the cost of this railway work?
The tendered cost of "Tender No. ECR-CAO-C-N-ETN-54-20-21 closing date 04-02-2021 " is ₹1.68 Cr (against an estimate of ₹1.41 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Tender No. ECR-CAO-C-N-ETN-54-20-21 closing date 04-02-2021 " is one of hundreds of railway works covered.