East Central RailwayOverdue

Supplying stacking spreading Pakur Range/Sahebganj loop machine crushed stone track ballast as per railway/RDSO sepecification on cess for Sagauli-Bettiah and Narkatiaganj-Harinagar section in connection with doubling of Sagauli-Vaimikinagar doubling project under CE/C/NKE.

Work #144
As of March 2026

Estimate Cost

₹16.40 Cr

Sanctioned estimate

Tendered Cost

₹19.17 Cr

+16.9% vs estimate

Physical Progress

75%

Work completed

Status

Overdue

Current stage

East Central Railway — CAO (Con)Overdue
Tendered₹19.17 Cr
Progress75%
Started15-03-2020
Target DOC31-03-2026

Work Details

5 Fields
Work No.
144
Agency
SHIVAM STONE WORKS Kolkata 18
hochominh sarani, bakultala behala chowrasta dc-wt-10, f-5 b kolkata-700001 west bengal, india.
Acceptance / LOA
LOA No.- CAO-C-HQ-Engineering/ECR-CAO-C-N-ETN-78-19-20/904160015087 dt.-05.02.2020
Officer in Charge
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar AEN/C/NKE
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹16.40 Cr
Tendered Cost
₹19.17 Cr
Physical Progress
75%
Date Started
15-03-2020
Original DOC
31-03-2026
Extended DOC
N/A

Supplying stacking spreading Pakur Range/Sahebganj loop machine crushed stone track ballast as per railway/RDSO sepecification on cess for Sagauli-Bettiah and Narkatiaganj-Harinagar section in connection with doubling of Sagauli-Vaimikinagar doubling project under CE/C/NKE. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s SHIVAM STONE WORKS Kolkata 18. The tendered cost of the work is ₹19.17 Cr, and it is currently Overdue with physical progress recorded at 75%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

DOC under process

?

Frequently Asked Questions

QWhat is the current status of the railway work "Supplying stacking spreading Pakur Range/Sahebganj loop machine crushed stone tr"?
Status: Overdue. This East Central Railway work is being executed by M/s SHIVAM STONE WORKS Kolkata 18. Physical progress stands at 75%. Current date of completion (DOC): 31-03-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s SHIVAM STONE WORKS Kolkata 18, hochominh sarani, bakultala behala chowrasta dc-wt-10, f-5 b kolkata-700001 west bengal, india.. Acceptance / agreement reference: LOA No.- CAO-C-HQ-Engineering/ECR-CAO-C-N-ETN-78-19-20/904160015087 dt.-05.02.2020. Work started on 15-03-2020.
QWhat is the cost of this railway work?
The tendered cost of "Supplying stacking spreading Pakur Range/Sahebganj loop mach" is ₹19.17 Cr (against an estimate of ₹16.40 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Supplying stacking spreading Pakur Range/Sahebganj loop mach" is one of hundreds of railway works covered.