Supplying and spreading of Blanketing, Ballast, supplying and laying boulder pitching over slopes of embankment, BG track linking, transportation of P.way material, dismantling of track, for diversion work of Br. No. 383B and 383C of VKNR-PNYA section including construction of two Girder bridge of VKNR-PNYA section.
Estimate Cost
₹17.21 Cr
Sanctioned estimate
Tendered Cost
₹18.87 Cr
+9.6% vs estimate
Physical Progress
0%
Work completed
Status
Overdue
Past target DOC
Work Details
5 FieldsCost, Progress & Timeline
6 FieldsSupplying and spreading of Blanketing, Ballast, supplying and laying boulder pitching over slopes of embankment, BG track linking, transportation of P.way material, dismantling of track, for diversion work of Br. No. 383B and 383C of VKNR-PNYA section including construction of two Girder bridge of VKNR-PNYA section. is an East Central Railway (ECR) infrastructure work in Bihar, executed by Bateshwar Singh-Begusarai. The tendered cost of the work is ₹18.87 Cr, and it is currently Overdue with physical progress recorded at 0%.
Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.
Frequently Asked Questions
- QWhat is the current status of the railway work "Supplying and spreading of Blanketing, Ballast, supplying and laying boulder pit"?
- Status: Overdue (overdue). This East Central Railway work is being executed by Bateshwar Singh-Begusarai. Physical progress stands at 0%. Current date of completion (DOC): 21-12-2025.
- QWho is the agency for this Bihar railway project?
- The agency for this work is Bateshwar Singh-Begusarai, Bihat, Tola Jagir, Begusarai-851135, India. Acceptance / agreement reference: ECR/ECRC/Civil/2023/0019 Date 12.06.2023. Work started on 02-08-2023.
- QWhat is the cost of this railway work?
- The tendered cost of "Supplying and spreading of Blanketing, Ballast, supplying an" is ₹18.87 Cr (against an estimate of ₹17.21 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
- QWhat railway works are tracked on BiharInfraTales?
- BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Supplying and spreading of Blanketing, Ballast, supplying an" is one of hundreds of railway works covered.