East Central RailwayIn Progress

Supplying, Fabrication, Erection and launching of open web Girders, supplying and fixing of H beam sleepers, track linking, Trolley refuse, Gang pathway etc and other associated works for Major Br. No. 322 (5x30.5m OWG), 352 (2X30.5M OWG) and 356 (1x30.5m OWG) UP line of NKE-VKNR section in connection with doubling of Narkatiaganj-Valmikinagar section under Dy.CE/Con/NKE.

Work #330
As of June 2026

Estimate Cost

₹15.50 Cr

Sanctioned estimate

Tendered Cost

₹13.99 Cr

-9.7% vs estimate

Physical Progress

25%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹13.99 Cr
Progress25%
Started05-02-2024
Target DOC10-11-2026
Vijay Kumar, CE/C/NE/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar, AEN/C/NKE

Work Details

5 Fields
Work No.
330
Acceptance / LOA
ECR/ECRC/Civil/2024/0036 Dt.19.04.2024
Officer in Charge
Vijay Kumar, CE/C/NE/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar, AEN/C/NKE
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹15.50 Cr
Tendered Cost
₹13.99 Cr
Physical Progress
25%
Date Started
05-02-2024
Original DOC
10-11-2026
Extended DOC
N/A

Supplying, Fabrication, Erection and launching of open web Girders, supplying and fixing of H beam sleepers, track linking, Trolley refuse, Gang pathway etc and other associated works for Major Br. No. 322 (5x30.5m OWG), 352 (2X30.5M OWG) and 356 (1x30.5m OWG) UP line of NKE-VKNR section in connection with doubling of Narkatiaganj-Valmikinagar section under Dy.CE/Con/NKE. is an East Central Railway (ECR) infrastructure work in Bihar, executed by BRBA Infratech LLP-Alipurduar. The tendered cost of the work is ₹13.99 Cr, and it is currently In Progress with physical progress recorded at 25%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Supplying, Fabrication, Erection and launching of open web Girders, supplying an"?
Status: In Progress. This East Central Railway work is being executed by BRBA Infratech LLP-Alipurduar. Physical progress stands at 25%. Current date of completion (DOC): 10-11-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is BRBA Infratech LLP-Alipurduar. Acceptance / agreement reference: ECR/ECRC/Civil/2024/0036 Dt.19.04.2024. Work started on 05-02-2024.
QWhat is the cost of this railway work?
The tendered cost of "Supplying, Fabrication, Erection and launching of open web G" is ₹13.99 Cr (against an estimate of ₹15.50 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Supplying, Fabrication, Erection and launching of open web G" is one of hundreds of railway works covered.