East Central RailwayIn Progress

Supplying of 1,00,000.00 cum 50 mm size machine crushed track ballast as per Railway RDSO's specification for B.G. Railway track & loading the same into any type of railway wagons F.O.R. Pakur/Bakudih siding various projects under CAO/Con/North, ECR.

Work #165
As of March 2026

Estimate Cost

₹14.88 Cr

Sanctioned estimate

Tendered Cost

₹19.64 Cr

+32.0% vs estimate

Physical Progress

29%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹19.64 Cr
Progress29%
Started28-04-2024
Target DOC15-04-2026
Indrajit Kumar, CE/C/NW; Mintu Kumar, Secy. to CAO/C/North; Vikash kumar XEN/Con /Ballast at Pakur

Work Details

5 Fields
Work No.
165
Acceptance / LOA
CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-72-23-24/00880550101125 dt. 16.04.2024 Agt. No. ECR/ECRC/Civil/2024/0010 dt. 01.04.2024
Officer in Charge
Indrajit Kumar, CE/C/NW; Mintu Kumar, Secy. to CAO/C/North; Vikash kumar XEN/Con /Ballast at Pakur
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹14.88 Cr
Tendered Cost
₹19.64 Cr
Physical Progress
29%
Date Started
28-04-2024
Original DOC
16-04-2025
Extended DOC
15-04-2026

Supplying of 1,00,000.00 cum 50 mm size machine crushed track ballast as per Railway RDSO's specification for B.G. Railway track & loading the same into any type of railway wagons F.O.R. Pakur/Bakudih siding various projects under CAO/Con/North, ECR. is an East Central Railway (ECR) infrastructure work in Bihar, executed by Cementone-Pakur. The tendered cost of the work is ₹19.64 Cr, and it is currently In Progress with physical progress recorded at 29%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work in progress.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Supplying of 1,00,000.00 cum 50 mm size machine crushed track ballast as per Rai"?
Status: In Progress. This East Central Railway work is being executed by Cementone-Pakur. Physical progress stands at 29%. Current date of completion (DOC): 15-04-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is Cementone-Pakur. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-72-23-24/00880550101125 dt. 16.04.2024 Agt. No. ECR/ECRC/Civil/2024/0010 dt. 01.04.2024. Work started on 28-04-2024.
QWhat is the cost of this railway work?
The tendered cost of "Supplying of 1,00,000.00 cum 50 mm size machine crushed trac" is ₹19.64 Cr (against an estimate of ₹14.88 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Supplying of 1,00,000.00 cum 50 mm size machine crushed trac" is one of hundreds of railway works covered.