East Central RailwayFinal Bill / Closure

Supply, Fabrication & Launching of Plate Girder, FOB & PF shed in connection with Gauge conversion work from Saharsa-Farbesganj section in Samastipur Division of East Central Railway

Work #36
As of March 2026

Estimate Cost

₹5.03 Cr

Sanctioned estimate

Tendered Cost

₹6.28 Cr

+24.9% vs estimate

Physical Progress

100%

Work completed

Status

Final Bill / Closure

Current stage

East Central Railway — CAO (Con)Final Bill / Closure
Tendered₹6.28 Cr
Progress100%
Started08-09-2015
Target DOC30-06-2022
Mahboob Alam CE/C/NC/MHX; Sri Pankaj Kumar Dy CE/C/III/SPJ; Sri A K Sinha AEN/C/DBG

Work Details

5 Fields
Work No.
36
Agency
Acceptance / LOA
ECR/CAO/Con/WT/27/North/14-15/1853 dt. 27.04.2015 ECR/CAO/Con/WT/Agt/32 dt 07.12.2015
Officer in Charge
Mahboob Alam CE/C/NC/MHX; Sri Pankaj Kumar Dy CE/C/III/SPJ; Sri A K Sinha AEN/C/DBG
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹5.03 Cr
Tendered Cost
₹6.28 Cr
Physical Progress
100%
Date Started
08-09-2015
Original DOC
30-06-2022
Extended DOC
N/A

Supply, Fabrication & Launching of Plate Girder, FOB & PF shed in connection with Gauge conversion work from Saharsa-Farbesganj section in Samastipur Division of East Central Railway is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Bimal Roy. The tendered cost of the work is ₹6.28 Cr, and it is currently Final Bill / Closure with physical progress recorded at 100%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work completed. Final variation approved & Final bill is under process.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Supply, Fabrication & Launching of Plate Girder, FOB & PF shed in connection wit"?
Status: Final Bill / Closure. This East Central Railway work is being executed by M/s Bimal Roy. Physical progress stands at 100%. Current date of completion (DOC): 30-06-2022.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Bimal Roy. Acceptance / agreement reference: ECR/CAO/Con/WT/27/North/14-15/1853 dt. 27.04.2015 ECR/CAO/Con/WT/Agt/32 dt 07.12.2015. Work started on 08-09-2015.
QWhat is the cost of this railway work?
The tendered cost of "Supply, Fabrication & Launching of Plate Girder, FOB & PF sh" is ₹6.28 Cr (against an estimate of ₹5.03 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Supply, Fabrication & Launching of Plate Girder, FOB & PF sh" is one of hundreds of railway works covered.