East Central RailwayIn Progress

Supply, fabrication, erection/launching of superstructure for major bridge No. 211 (1X18.3m) at Km 97.265, 220 (1X24.4m) at Km 99.221, 228 (1X45.7m) Km 102.565, 306 (1X30.5m) at Km 124.129, 316 (6X24.4m) at Km 126.557, 336 (2X30.5m) at Km 131.58, 340 (1X45.7m) at Km 132.884, 347 (1X24.4m) at Km 135.187, 351 (2X24.4m) at Km 136.609, 361 (3X45.7m) at Km 139.075, 365 (1X45.7m) at km 140.052 and 379 (1X45.7m) at Km 144.673 between Kesaria-Sagauli in connection with construction of Hajipur-Sugauli New rail Line project

Estimate Cost

₹41.81 Cr

Sanctioned estimate

Tendered Cost

₹39.12 Cr

-6.4% vs estimate

Physical Progress

1%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹39.12 Cr
Progress1%
Started21-02-2024
Target DOC31-12-2026
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP

Work Details

5 Fields
Work No.
292
Acceptance / LOA
CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-45-23-24 / 00819610098125 dt 21.02.24
Officer in Charge
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹41.81 Cr
Tendered Cost
₹39.12 Cr
Physical Progress
1%
Date Started
21-02-2024
Original DOC
20-11-2025
Extended DOC
31-12-2026

Supply, fabrication, erection/launching of superstructure for major bridge No. 211 (1X18.3m) at Km 97.265, 220 (1X24.4m) at Km 99.221, 228 (1X45.7m) Km 102.565, 306 (1X30.5m) at Km 124.129, 316 (6X24.4m) at Km 126.557, 336 (2X30.5m) at Km 131.58, 340 (1X45.7m) at Km 132.884, 347 (1X24.4m) at Km 135.187, 351 (2X24.4m) at Km 136.609, 361 (3X45.7m) at Km 139.075, 365 (1X45.7m) at km 140.052 and 379 (1X45.7m) at Km 144.673 between Kesaria-Sagauli in connection with construction of Hajipur-Sugauli New rail Line project is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Galvano India Private Limited-Uttar Pradesh. The tendered cost of the work is ₹39.12 Cr, and it is currently In Progress with physical progress recorded at 1%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Supply, fabrication, erection/launching of superstructure for major bridge No. 2"?
Status: In Progress. This East Central Railway work is being executed by M/s Galvano India Private Limited-Uttar Pradesh. Physical progress stands at 1%. Current date of completion (DOC): 31-12-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Galvano India Private Limited-Uttar Pradesh. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-45-23-24 / 00819610098125 dt 21.02.24. Work started on 21-02-2024.
QWhat is the cost of this railway work?
The tendered cost of "Supply, fabrication, erection/launching of superstructure fo" is ₹39.12 Cr (against an estimate of ₹41.81 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Supply, fabrication, erection/launching of superstructure fo" is one of hundreds of railway works covered.