East Central RailwayCompleted

Supply Fabrication and erection of 30.5m and 45.7m span of open web steel girder (25 ton) loading standard: Br. No. 123 (2x30.5m) at Km.151/4-5, Br. No. 113 & 114 (3x30.5m) at Km.146/14-147/2, Br.No. 92 (1x45.7m) Km.139/11-12, Br. No. 88 (2x30.5) Km.138/5-6 between Forbesganj-Narpatganj, Br. No.73 (4x30.5m) at Km.131/4-7 between Narpatganj-Lalitpur, Br.No.52 (2x45.7) at Km.120/1-3 between Lalitpur-Pratapganj, Br.No. 38 (3x30.5m) at Km.111/10-12 between Pratapganj-Raghopur, Br. No. 19A (1X30.58M) at Km.60/1-2 between Garhbaruri-Supaul in connection with gauge conversion work from Saharsa to Forbesganj.

Work #206
As of June 2026

Estimate Cost

₹24.21 Cr

Sanctioned estimate

Tendered Cost

₹20.99 Cr

-13.3% vs estimate

Physical Progress

100%

Work completed

Status

Completed

Current stage

East Central Railway — CAO (Con)Completed
Tendered₹20.99 Cr
Progress100%
Started30-12-2012
Target DOC30-06-2022
Satya Prakash Yadav, CE/C/N/MHX; Pankaj Kr, Dy CE/C/III/SPJ; A K Sinha, AEN/C/DBG

Work Details

5 Fields
Work No.
206
Acceptance / LOA
ECR/CAO/Con/WT/108/North/4710 dt. 11.12.2012; ECR/CAO/Con/WT/Agt/50 Dt 28.10.13
Officer in Charge
Satya Prakash Yadav, CE/C/N/MHX; Pankaj Kr, Dy CE/C/III/SPJ; A K Sinha, AEN/C/DBG
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹24.21 Cr
Tendered Cost
₹20.99 Cr
Physical Progress
100%
Date Started
30-12-2012
Original DOC
30-06-2022
Extended DOC
N/A

Supply Fabrication and erection of 30.5m and 45.7m span of open web steel girder (25 ton) loading standard: Br. No. 123 (2x30.5m) at Km.151/4-5, Br. No. 113 & 114 (3x30.5m) at Km.146/14-147/2, Br.No. 92 (1x45.7m) Km.139/11-12, Br. No. 88 (2x30.5) Km.138/5-6 between Forbesganj-Narpatganj, Br. No.73 (4x30.5m) at Km.131/4-7 between Narpatganj-Lalitpur, Br.No.52 (2x45.7) at Km.120/1-3 between Lalitpur-Pratapganj, Br.No. 38 (3x30.5m) at Km.111/10-12 between Pratapganj-Raghopur, Br. No. 19A (1X30.58M) at Km.60/1-2 between Garhbaruri-Supaul in connection with gauge conversion work from Saharsa to Forbesganj. is an East Central Railway (ECR) infrastructure work in Bihar, executed by JYOTI Forge & Fabrication. The tendered cost of the work is ₹20.99 Cr, and it is currently Completed with physical progress recorded at 100%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

tendered_cost_crore raw: 20.99 After 1st Variation 22.59

?

Frequently Asked Questions

QWhat is the current status of the railway work "Supply Fabrication and erection of 30.5m and 45.7m span of open web steel girder"?
Status: Completed. This East Central Railway work is being executed by JYOTI Forge & Fabrication. Physical progress stands at 100%. Current date of completion (DOC): 30-06-2022.
QWho is the agency for this Bihar railway project?
The agency for this work is JYOTI Forge & Fabrication. Acceptance / agreement reference: ECR/CAO/Con/WT/108/North/4710 dt. 11.12.2012; ECR/CAO/Con/WT/Agt/50 Dt 28.10.13. Work started on 30-12-2012.
QWhat is the cost of this railway work?
The tendered cost of "Supply Fabrication and erection of 30.5m and 45.7m span of o" is ₹20.99 Cr (against an estimate of ₹24.21 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Supply Fabrication and erection of 30.5m and 45.7m span of o" is one of hundreds of railway works covered.