East Central RailwayIn Progress

Construction of Station building, Service building, S&T buildings, Electrical buildings, Residential building, Approach road, High level Platform, Wharf, PP shed, FOB, Circulating area, Height gauge and other Miscellaneous works between Supaul–Triveniganj section in connection with new rail line project of Araria-Supaul in Samastipur division of East Central Railway.

Work #227
As of June 2026

Estimate Cost

₹116.58 Cr

Sanctioned estimate

Tendered Cost

₹114.11 Cr

-2.1% vs estimate

Physical Progress

90%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹114.11 Cr
Progress90%
Started15-03-2024
Target DOC01-03-2027
Satya Prakash Yadav, CE/C/N/MHX; Pankaj Kr, Dy CE/C/III/SPJ; A K Sinha, AEN/C/DBG

Work Details

5 Fields
Work No.
227
Acceptance / LOA
CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-07-23-24/00823450097013; ECR/ECRC/Civil/2024/0044
Officer in Charge
Satya Prakash Yadav, CE/C/N/MHX; Pankaj Kr, Dy CE/C/III/SPJ; A K Sinha, AEN/C/DBG
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹116.58 Cr
Tendered Cost
₹114.11 Cr
Physical Progress
90%
Date Started
15-03-2024
Original DOC
01-03-2027
Extended DOC
N/A

Construction of Station building, Service building, S&T buildings, Electrical buildings, Residential building, Approach road, High level Platform, Wharf, PP shed, FOB, Circulating area, Height gauge and other Miscellaneous works between Supaul–Triveniganj section in connection with new rail line project of Araria-Supaul in Samastipur division of East Central Railway. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Hari-GPT JV. The tendered cost of the work is ₹114.11 Cr, and it is currently In Progress with physical progress recorded at 90%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of Station building, Service building, S&T buildings, Electrical bu"?
Status: In Progress. This East Central Railway work is being executed by M/s Hari-GPT JV. Physical progress stands at 90%. Current date of completion (DOC): 01-03-2027.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Hari-GPT JV. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-07-23-24/00823450097013; ECR/ECRC/Civil/2024/0044. Work started on 15-03-2024.
QWhat is the cost of this railway work?
The tendered cost of "Construction of Station building, Service building, S&T buil" is ₹114.11 Cr (against an estimate of ₹116.58 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of Station building, Service building, S&T buil" is one of hundreds of railway works covered.