East Central RailwayIn Progress

Construction of Station building, Platform, PP Shelter, Subway, approach road, development of circulating area, boundary wall, drain, RUB's earthwrk in yard and other misc. Work at Harsiddhi Station & Rampur Halt in connection with construction of Hajipur Sagauli New rail Line project

Work #108
As of March 2026

Estimate Cost

₹56.37 Cr

Sanctioned estimate

Tendered Cost

₹51.26 Cr

-9.1% vs estimate

Physical Progress

1%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹51.26 Cr
Progress1%
Started18-12-2023
Target DOC31-07-2026
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; K K Bharti, AEN/C/Kesaria

Work Details

5 Fields
Work No.
108
Agency
REL-AIL JV, Goharua House
19, Patliputra colony, Patna-800014
Acceptance / LOA
CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-38-23-24/01141610093439 dt 18.12.23
Officer in Charge
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; K K Bharti, AEN/C/Kesaria
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹56.37 Cr
Tendered Cost
₹51.26 Cr
Physical Progress
1%
Date Started
18-12-2023
Original DOC
17-09-2025
Extended DOC
31-07-2026

Construction of Station building, Platform, PP Shelter, Subway, approach road, development of circulating area, boundary wall, drain, RUB's earthwrk in yard and other misc. Work at Harsiddhi Station & Rampur Halt in connection with construction of Hajipur Sagauli New rail Line project is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s REL-AIL JV. The tendered cost of the work is ₹51.26 Cr, and it is currently In Progress with physical progress recorded at 1%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work in progress

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of Station building, Platform, PP Shelter, Subway, approach road, d"?
Status: In Progress. This East Central Railway work is being executed by M/s REL-AIL JV. Physical progress stands at 1%. Current date of completion (DOC): 31-07-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s REL-AIL JV, Goharua House, 19, Patliputra colony, Patna-800014. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-38-23-24/01141610093439 dt 18.12.23. Work started on 18-12-2023.
QWhat is the cost of this railway work?
The tendered cost of "Construction of Station building, Platform, PP Shelter, Subw" is ₹51.26 Cr (against an estimate of ₹56.37 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of Station building, Platform, PP Shelter, Subw" is one of hundreds of railway works covered.