Construction of S&T building, passenger amenities and other misc. works i.e. providing and fixing lifting barrier at level crossing, construction of gate lodge, staff quarters, platform wall etc. between Samastipur-Darbhanga station in connection with SPJ-DBG doubling.
Estimate Cost
₹40.32 Cr
Sanctioned estimate
Tendered Cost
₹42.04 Cr
+4.3% vs estimate
Physical Progress
87%
Work completed
Status
Overdue
Past target DOC
Work Details
5 FieldsCost, Progress & Timeline
6 FieldsConstruction of S&T building, passenger amenities and other misc. works i.e. providing and fixing lifting barrier at level crossing, construction of gate lodge, staff quarters, platform wall etc. between Samastipur-Darbhanga station in connection with SPJ-DBG doubling. is an East Central Railway (ECR) infrastructure work in Bihar, executed by Kumar Heights Private Limited. The tendered cost of the work is ₹42.04 Cr, and it is currently Overdue with physical progress recorded at 87%.
Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.
Remarks
DOC extension sought from contractor.
Frequently Asked Questions
- QWhat is the current status of the railway work "Construction of S&T building, passenger amenities and other misc. works i.e. pro"?
- Status: Overdue (overdue). This East Central Railway work is being executed by Kumar Heights Private Limited. Physical progress stands at 87%. Current date of completion (DOC): 31-03-2024.
- QWho is the agency for this Bihar railway project?
- The agency for this work is Kumar Heights Private Limited, 302, Hem Plaza, Freser Road, Patna-800001.. Acceptance / agreement reference: ECR/CAO/C/WT/16/N/16-17/10731 Dt 20.10.2016 ** ECR/CAO/Con/WT/Agt/24 dt.28.02.17. Work started on 08-12-2016.
- QWhat is the cost of this railway work?
- The tendered cost of "Construction of S&T building, passenger amenities and other " is ₹42.04 Cr (against an estimate of ₹40.32 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
- QWhat railway works are tracked on BiharInfraTales?
- BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of S&T building, passenger amenities and other " is one of hundreds of railway works covered.