East Central RailwayOverdue

Construction of S&T building, passenger amenities and other misc. works i.e. providing and fixing lifting barrier at level crossing, construction of gate lodge, staff quarters, platform wall etc. between Samastipur-Darbhanga station in connection with SPJ-DBG doubling.

Work #10
As of March 2026

Estimate Cost

₹40.32 Cr

Sanctioned estimate

Tendered Cost

₹42.04 Cr

+4.3% vs estimate

Physical Progress

87%

Work completed

Status

Overdue

Past target DOC

East Central Railway — CAO (Con)Overdue
Tendered₹42.04 Cr
Progress87%
Started08-12-2016
Target DOC31-03-2024
Mahboob Alam CE/C/NC/MHX; Vinod Kumar Gupta, Dy CE/C/I/SPJ; Vijay Shankar Singh, AEN/C/SPJ

Work Details

5 Fields
Work No.
10
Agency
Kumar Heights Private Limited
302, Hem Plaza, Freser Road, Patna-800001.
Acceptance / LOA
ECR/CAO/C/WT/16/N/16-17/10731 Dt 20.10.2016 ** ECR/CAO/Con/WT/Agt/24 dt.28.02.17
Officer in Charge
Mahboob Alam CE/C/NC/MHX; Vinod Kumar Gupta, Dy CE/C/I/SPJ; Vijay Shankar Singh, AEN/C/SPJ
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹40.32 Cr
Tendered Cost
₹42.04 Cr
Physical Progress
87%
Date Started
08-12-2016
Original DOC
19-07-2017
Extended DOC
31-03-2024

Construction of S&T building, passenger amenities and other misc. works i.e. providing and fixing lifting barrier at level crossing, construction of gate lodge, staff quarters, platform wall etc. between Samastipur-Darbhanga station in connection with SPJ-DBG doubling. is an East Central Railway (ECR) infrastructure work in Bihar, executed by Kumar Heights Private Limited. The tendered cost of the work is ₹42.04 Cr, and it is currently Overdue with physical progress recorded at 87%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

DOC extension sought from contractor.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of S&T building, passenger amenities and other misc. works i.e. pro"?
Status: Overdue (overdue). This East Central Railway work is being executed by Kumar Heights Private Limited. Physical progress stands at 87%. Current date of completion (DOC): 31-03-2024.
QWho is the agency for this Bihar railway project?
The agency for this work is Kumar Heights Private Limited, 302, Hem Plaza, Freser Road, Patna-800001.. Acceptance / agreement reference: ECR/CAO/C/WT/16/N/16-17/10731 Dt 20.10.2016 ** ECR/CAO/Con/WT/Agt/24 dt.28.02.17. Work started on 08-12-2016.
QWhat is the cost of this railway work?
The tendered cost of "Construction of S&T building, passenger amenities and other " is ₹42.04 Cr (against an estimate of ₹40.32 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of S&T building, passenger amenities and other " is one of hundreds of railway works covered.