East Central RailwayIn Progress

Manufacturing, fabricating, Instalation of glued insulated joint 60Kg/52Kg (In situ) between Narkatiaganj-Valmikinagar in connection with doubling project of NKE-VKNR under juridiction of DY.CE/Con/NKE

Estimate Cost

₹1.48 Cr

Sanctioned estimate

Tendered Cost

₹1.48 Cr

0.0% vs estimate

Physical Progress

77%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹1.48 Cr
Progress77%
Started22-03-2022
Target DOC15-06-2026
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Harinandan Ram AEN/C/NKE

Work Details

5 Fields
Work No.
151
Acceptance / LOA
CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-52-20-21/00922790033972
Officer in Charge
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Harinandan Ram AEN/C/NKE
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹1.48 Cr
Tendered Cost
₹1.48 Cr
Physical Progress
77%
Date Started
22-03-2022
Original DOC
15-06-2026
Extended DOC
N/A

Manufacturing, fabricating, Instalation of glued insulated joint 60Kg/52Kg (In situ) between Narkatiaganj-Valmikinagar in connection with doubling project of NKE-VKNR under juridiction of DY.CE/Con/NKE is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s EDEN VINIMAY PRIVATE LIMITED- KOLKATA 22 Strand Road Groun…. The tendered cost of the work is ₹1.48 Cr, and it is currently In Progress with physical progress recorded at 77%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work in progress.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Manufacturing, fabricating, Instalation of glued insulated joint 60Kg/52Kg (In s"?
Status: In Progress. This East Central Railway work is being executed by M/s EDEN VINIMAY PRIVATE LIMITED- KOLKATA 22 Strand Road Groun…. Physical progress stands at 77%. Current date of completion (DOC): 15-06-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s EDEN VINIMAY PRIVATE LIMITED- KOLKATA 22 Strand Road Ground Floor, Kolkata -700001 West Bengal, India. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-52-20-21/00922790033972. Work started on 22-03-2022.
QWhat is the cost of this railway work?
The tendered cost of "Manufacturing, fabricating, Instalation of glued insulated j" is ₹1.48 Cr (against an estimate of ₹1.48 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Manufacturing, fabricating, Instalation of glued insulated j" is one of hundreds of railway works covered.