East Central RailwayIn Progress

Linking BG Track, spreading of ballast carriage of P.way materials, spreading of PSC sleeper, linking and packing of points and crossings etc. in connection with 3rd & 4th line work of Barauni-Bachhwara section project including Barauni yard remodiling in Sonpur Division ECR.

Work #27
As of March 2026

Estimate Cost

₹24.01 Cr

Sanctioned estimate

Tendered Cost

₹21.46 Cr

-10.6% vs estimate

Physical Progress

10%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹21.46 Cr
Progress10%
Started03-06-2025
Target DOC31-07-2026
Mahboob Alam CE/C/NC/MHX; Avinash Sahani. Dy.CE/C/II/SPJ

Work Details

5 Fields
Work No.
27
Acceptance / LOA
CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-70-23-24/00999530104382 dt. 03.06.2024
Officer in Charge
Mahboob Alam CE/C/NC/MHX; Avinash Sahani. Dy.CE/C/II/SPJ
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹24.01 Cr
Tendered Cost
₹21.46 Cr
Physical Progress
10%
Date Started
03-06-2025
Original DOC
31-07-2026
Extended DOC
N/A

Linking BG Track, spreading of ballast carriage of P.way materials, spreading of PSC sleeper, linking and packing of points and crossings etc. in connection with 3rd & 4th line work of Barauni-Bachhwara section project including Barauni yard remodiling in Sonpur Division ECR. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Ramniwas Singh Begusarai. The tendered cost of the work is ₹21.46 Cr, and it is currently In Progress with physical progress recorded at 10%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work In progress

?

Frequently Asked Questions

QWhat is the current status of the railway work "Linking BG Track, spreading of ballast carriage of P.way materials, spreading of"?
Status: In Progress. This East Central Railway work is being executed by M/s Ramniwas Singh Begusarai. Physical progress stands at 10%. Current date of completion (DOC): 31-07-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Ramniwas Singh Begusarai. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-70-23-24/00999530104382 dt. 03.06.2024. Work started on 03-06-2025.
QWhat is the cost of this railway work?
The tendered cost of "Linking BG Track, spreading of ballast carriage of P.way mat" is ₹21.46 Cr (against an estimate of ₹24.01 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Linking BG Track, spreading of ballast carriage of P.way mat" is one of hundreds of railway works covered.