East Central RailwayFinal Bill / Closure

Provision of infrastructure related with mining of level crossing between SHC-FBG blanketing work between SHC-SRGR section other misc. work related with GC work of SHC-FBG section

Work #38
As of March 2026

Estimate Cost

₹39.28 Cr

Sanctioned estimate

Tendered Cost

₹43.13 Cr

+9.8% vs estimate

Physical Progress

100%

Work completed

Status

Final Bill / Closure

Current stage

East Central Railway — CAO (Con)Final Bill / Closure
Tendered₹43.13 Cr
Progress100%
Started15-05-2018
Target DOC31-07-2024
Mahboob Alam CE/C/NC/MHX; Sri Pankaj Kumar Dy CE/C/III/SPJ; Sri H R Chaudhary AEN/C/SRGR

Work Details

5 Fields
Work No.
38
Acceptance / LOA
ECR/CAO/Con/WT/E-Tender/North/53/17-18/2515 dated 10.05.2018. ECR/CAO/Con/WT/Agt/15 Dt. 13.07.2018
Officer in Charge
Mahboob Alam CE/C/NC/MHX; Sri Pankaj Kumar Dy CE/C/III/SPJ; Sri H R Chaudhary AEN/C/SRGR
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹39.28 Cr
Tendered Cost
₹43.13 Cr
Physical Progress
100%
Date Started
15-05-2018
Original DOC
31-07-2024
Extended DOC
N/A

Provision of infrastructure related with mining of level crossing between SHC-FBG blanketing work between SHC-SRGR section other misc. work related with GC work of SHC-FBG section is an East Central Railway (ECR) infrastructure work in Bihar, executed by Dooars Construction Co.. The tendered cost of the work is ₹43.13 Cr, and it is currently Final Bill / Closure with physical progress recorded at 100%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work completed. Final variation & Final bill is under process.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Provision of infrastructure related with mining of level crossing between SHC-FB"?
Status: Final Bill / Closure. This East Central Railway work is being executed by Dooars Construction Co.. Physical progress stands at 100%. Current date of completion (DOC): 31-07-2024.
QWho is the agency for this Bihar railway project?
The agency for this work is Dooars Construction Co.. Acceptance / agreement reference: ECR/CAO/Con/WT/E-Tender/North/53/17-18/2515 dated 10.05.2018. ECR/CAO/Con/WT/Agt/15 Dt. 13.07.2018. Work started on 15-05-2018.
QWhat is the cost of this railway work?
The tendered cost of "Provision of infrastructure related with mining of level cro" is ₹43.13 Cr (against an estimate of ₹39.28 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Provision of infrastructure related with mining of level cro" is one of hundreds of railway works covered.