East Central RailwayIn Progress

Balance work (i.e. construction of 3 nos. gate lodges, approach road of 22 nos. LCs, etc. at JNKR, BNKI, Rupuli Halt & Harpati Halt, FOB at BNKI, shifting of P/F sheds, etc.) at JNKR between Dauram Madhepura to Banmankhi.

Work #174
As of June 2026

Estimate Cost

₹5.84 Cr

Sanctioned estimate

Tendered Cost

₹8.21 Cr

+40.6% vs estimate

Physical Progress

87%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹8.21 Cr
Progress87%
Started15-03-2012
Target DOC30-11-2026
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/I/SPJ; Rakesh Ranjan, AEN/C/SPJ

Work Details

5 Fields
Work No.
174
Agency
J.S. Company
At+Po.-Bihat, distt.-Begusarai.
Acceptance / LOA
W/C/247/SHC/II/Tender/no 09 of 2010-11 (Open) Dt 13.01.12 ** ECR/CAO/Con/WT/Agt/34 dt. 30.06.13
Officer in Charge
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/I/SPJ; Rakesh Ranjan, AEN/C/SPJ
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹5.84 Cr
Tendered Cost
₹8.21 Cr
Physical Progress
87%
Date Started
15-03-2012
Original DOC
12-10-2012
Extended DOC
30-11-2026

Balance work (i.e. construction of 3 nos. gate lodges, approach road of 22 nos. LCs, etc. at JNKR, BNKI, Rupuli Halt & Harpati Halt, FOB at BNKI, shifting of P/F sheds, etc.) at JNKR between Dauram Madhepura to Banmankhi. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s J.S. Company. The tendered cost of the work is ₹8.21 Cr, and it is currently In Progress with physical progress recorded at 87%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Balance work (i.e. construction of 3 nos. gate lodges, approach road of 22 nos. "?
Status: In Progress. This East Central Railway work is being executed by M/s J.S. Company. Physical progress stands at 87%. Current date of completion (DOC): 30-11-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s J.S. Company, At+Po.-Bihat, distt.-Begusarai.. Acceptance / agreement reference: W/C/247/SHC/II/Tender/no 09 of 2010-11 (Open) Dt 13.01.12 ** ECR/CAO/Con/WT/Agt/34 dt. 30.06.13. Work started on 15-03-2012.
QWhat is the cost of this railway work?
The tendered cost of "Balance work (i.e. construction of 3 nos. gate lodges, appro" is ₹8.21 Cr (against an estimate of ₹5.84 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Balance work (i.e. construction of 3 nos. gate lodges, appro" is one of hundreds of railway works covered.