East Central RailwayOverdue

Final Location servey for Raxaul-Kathmandu new electrified rail link (funded by MEA) (136 Km).

Work #137
As of March 2026

Estimate Cost

₹36.39 Cr

Sanctioned estimate

Tendered Cost

₹30.44 Cr

-16.4% vs estimate

Physical Progress

95%

Work completed

Status

Overdue

Current stage

East Central Railway — CAO (Con)Overdue
Tendered₹30.44 Cr
Progress95%
Started04-01-2021
Target DOC31-03-2026
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar AEN/C/NKE

Work Details

5 Fields
Work No.
137
Agency
Konkan Railway corporation Limited
Balapur Bhawan, Sector-II, CBD, Belapur, Navi, Mumbai- 400614
Acceptance / LOA
LOA No ECR/CAO/Con/North/Single-01-19-20 dated 13.03.2020
Officer in Charge
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar AEN/C/NKE
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹36.39 Cr
Tendered Cost
₹30.44 Cr
Physical Progress
95%
Date Started
04-01-2021
Original DOC
31-03-2026
Extended DOC
N/A

Final Location servey for Raxaul-Kathmandu new electrified rail link (funded by MEA) (136 Km). is an East Central Railway (ECR) infrastructure work in Bihar, executed by Konkan Railway corporation Limited. The tendered cost of the work is ₹30.44 Cr, and it is currently Overdue with physical progress recorded at 95%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

DOC under process

?

Frequently Asked Questions

QWhat is the current status of the railway work "Final Location servey for Raxaul-Kathmandu new electrified rail link (funded by "?
Status: Overdue. This East Central Railway work is being executed by Konkan Railway corporation Limited. Physical progress stands at 95%. Current date of completion (DOC): 31-03-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is Konkan Railway corporation Limited, Balapur Bhawan, Sector-II, CBD, Belapur, Navi, Mumbai- 400614. Acceptance / agreement reference: LOA No ECR/CAO/Con/North/Single-01-19-20 dated 13.03.2020. Work started on 04-01-2021.
QWhat is the cost of this railway work?
The tendered cost of "Final Location servey for Raxaul-Kathmandu new electrified r" is ₹30.44 Cr (against an estimate of ₹36.39 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Final Location servey for Raxaul-Kathmandu new electrified r" is one of hundreds of railway works covered.