East Central RailwayIn Progress

E-Tender No. ECR-CAO-C-N-ETN-78-19-20 closing date 01-11-2019 for Supplying stacking, spreading Pakur Range/Sahebganj loop machine crushed stone track ballast as per Railway/RDSO specification on cess for Sagauli-Bettiah and Narkatiaganj-Harinagar section in c/w doubling of Sagauli-Valmikinagar doubling project under CE/Con/NE.

Work #304
As of June 2026

Estimate Cost

₹16.40 Cr

Sanctioned estimate

Tendered Cost

₹19.17 Cr

+16.9% vs estimate

Physical Progress

99%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹19.17 Cr
Progress99%
Started05-02-2020
Target DOC31-03-2026
Sri Indrajit Kumar, CE/C/NW; Sri Ajay Kumar, Dy.CE/C/BTH; Sri Nirmal Shalhata, AEN/Con/II/BTH

Work Details

5 Fields
Work No.
304
Agency
Shivam Stone Works-Kolkata
18 Hochominh Sarani, Bakultala Behala Chowrasra, DCW-T-10, F-5B, Kolkata-700001, West Bengal, India
Acceptance / LOA
ECR/CAO/Con/WT/Agt./107 dated. 22.06.2020
Officer in Charge
Sri Indrajit Kumar, CE/C/NW; Sri Ajay Kumar, Dy.CE/C/BTH; Sri Nirmal Shalhata, AEN/Con/II/BTH
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹16.40 Cr
Tendered Cost
₹19.17 Cr
Physical Progress
99%
Date Started
05-02-2020
Original DOC
04-07-2020
Extended DOC
31-03-2026

E-Tender No. ECR-CAO-C-N-ETN-78-19-20 closing date 01-11-2019 for Supplying stacking, spreading Pakur Range/Sahebganj loop machine crushed stone track ballast as per Railway/RDSO specification on cess for Sagauli-Bettiah and Narkatiaganj-Harinagar section in c/w doubling of Sagauli-Valmikinagar doubling project under CE/Con/NE. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Shivam Stone Works-Kolkata. The tendered cost of the work is ₹19.17 Cr, and it is currently In Progress with physical progress recorded at 99%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "E-Tender No. ECR-CAO-C-N-ETN-78-19-20 closing date 01-11-2019 for Supplying stac"?
Status: In Progress. This East Central Railway work is being executed by M/s Shivam Stone Works-Kolkata. Physical progress stands at 99%. Current date of completion (DOC): 31-03-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Shivam Stone Works-Kolkata, 18 Hochominh Sarani, Bakultala Behala Chowrasra, DCW-T-10, F-5B, Kolkata-700001, West Bengal, India. Acceptance / agreement reference: ECR/CAO/Con/WT/Agt./107 dated. 22.06.2020. Work started on 05-02-2020.
QWhat is the cost of this railway work?
The tendered cost of "E-Tender No. ECR-CAO-C-N-ETN-78-19-20 closing date 01-11-201" is ₹19.17 Cr (against an estimate of ₹16.40 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "E-Tender No. ECR-CAO-C-N-ETN-78-19-20 closing date 01-11-201" is one of hundreds of railway works covered.