Routine Maintenance and Incident Management of Two laning of Muzaffarpur-Barauni Section of NH-122 (Old NH-28) from 519.600 to 627.163 in the state of Bihar.
Physical Progress
0.0%
Drone-monitored
Financial Progress
0.0%
Of awarded cost
Awarded Cost
₹6 Cr
Contract value
Length
107.563 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
9016
Aerial captures
Project Progress
Stage
Under O&M through OMT/TOT/O&M Agency at Site
Due Date
21-05-2026
Likely Date
-
Completion
0.0%
Physical Done
Project Timeline
Awarded
22-05-2025
Construction Started
22-05-2025
In Progress
Near Completion
-
Completed
-
Physical vs Financial Progress
Project Details
UPC
N/06011/01003/BR
National Highway
122
Regional Office
RO-Patna
State
Bihar
Mode
Item Rate
Length
107.563 km
Contractor
Rehabilitation Engineering (prop. Hemangini Bharatchandra Shewale)
Project Stage
Under O&M through OMT/TOT/O&M Agency at Site
Drone Frames
9016 frames
Last Flight
2026-04-26
Cost & Timeline
Awarded Cost
₹5.81 Cr
Capital Cost
N/A
Start Date
22-05-2025
PCOD Date
-
Scheduled Completion
21-05-2026
Likely Completion
-
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-08-03 14:13:18
Contractor Profile
Rehabilitation Engineering (prop. Hemangini Bharatchandra Shewale)
Project Intelligence
Physical progress stands at 0.0%. Financial utilization at 0.0%.
Project is on schedule or ahead of planned completion date.
Covers 107.563 km on 122, improving regional connectivity.
9016 drone frames uploaded — real-time aerial monitoring is active for this project.
Routine Maintenance and Incident Management of Two laning of Muzaffarpur-Barauni Section of NH-122 (Old NH-28) from 519.600 to 627.163 in the state of Bihar. is a National Highways Authority of India (NHAI) project on 122 in Bihar. The project has an awarded cost of ₹5.81 Cr and is currently ongoing with physical progress at 0.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
9,016 frames · NHAI surveillance footage · UPC N/06011/01003/BR
Frequently Asked Questions
- QWhat is the current status of the NHAI project "Routine Maintenance and Incident Management of Two laning of Muzaffarpur-Barauni"?
- Current physical progress: 0.0%. Financial progress: 0.0%. Project stage: Under O&M through OMT/TOT/O&M Agency at Site. On schedule. Scheduled completion: 21-05-2026. Likely completion: -.
- QWho is the contractor for this NHAI highway project?
- The contractor for Routine Maintenance and Incident Management of Two laning of Muzaffarpur-Barauni Section of NH-122 (Old NH-28) from 519.600 to 627.163 in the state of Bihar. is Rehabilitation Engineering (prop. Hemangini Bharatchandra Shewale). The project is under RO-Patna and covers 107.563 km on 122.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹5.81 Crore. The project is on 122 in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/06011/01003/BR in NHAI?
- UPC (Unique Project Code) N/06011/01003/BR refers to "Routine Maintenance and Incident Management of Two laning of Muzaffarpur-Barauni Section of NH-122 (Old NH-28) from 519.600 to 627.163 in the state of Bihar. " — a National Highway project on 122 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.