Muzaffarpur - Sonbarsa Section of NH-77 from km 2.800 to km 89.000
Physical Progress
100.0%
Drone-monitored
Financial Progress
100.0%
Of awarded cost
Awarded Cost
₹1834 Cr
Contract value
Length
82.08 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
6623
Aerial captures
Project Progress
Stage
CC Issued & O&M by Construction Agency
Due Date
25-11-2013
Likely Date
30-06-2026
Completion
100.0%
Physical Done
Project Timeline
Awarded
30-05-2011
Construction Started
30-05-2011
In Progress
Near Completion
29-06-2015
Completed
30-06-2026
Physical vs Financial Progress
Project Details
UPC
N/09073/01001/BR
National Highway
77
Regional Office
RO-Patna
State
Bihar
Mode
BOT Annuity
Length
82.08 km
Contractor
BSC - C&C (JV)
Project Stage
CC Issued & O&M by Construction Agency
Drone Frames
6623 frames
Last Flight
2025-08-23
Cost & Timeline
Awarded Cost
₹1834.00 Cr
Capital Cost
₹2290.72 Cr
Start Date
30-05-2011
PCOD Date
29-06-2015
Scheduled Completion
25-11-2013
Likely Completion
30-06-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 17:44:26
Contractor Profile
BSC - C&C (JV)
Project Intelligence
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 82.08 km on 77, improving regional connectivity.
6623 drone frames uploaded — real-time aerial monitoring is active for this project.
Muzaffarpur - Sonbarsa Section of NH-77 from km 2.800 to km 89.000 is a National Highways Authority of India (NHAI) project on 77 in Bihar. The project has an awarded cost of ₹1834.00 Cr and is currently 1 with physical progress at 100.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
6,623 frames · NHAI surveillance footage · UPC N/09073/01001/BR
Frequently Asked Questions
- What is the current status of the NHAI project "Muzaffarpur - Sonbarsa Section of NH-77 from km 2.800 to km 89.000"?
- Current physical progress: 100.0%. Financial progress: 100.0%. Project stage: CC Issued & O&M by Construction Agency. On schedule. Scheduled completion: 25-11-2013. Likely completion: 30-06-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for Muzaffarpur - Sonbarsa Section of NH-77 from km 2.800 to km 89.000 is BSC - C&C (JV). The project is under RO-Patna and covers 82.08 km on 77.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹1834.00 Crore. Total capital cost: ₹2290.72 Crore. The project is on 77 in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/09073/01001/BR in NHAI?
- UPC (Unique Project Code) N/09073/01001/BR refers to "Muzaffarpur - Sonbarsa Section of NH-77 from km 2.800 to km 89.000" — a National Highway project on 77 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.