Physical Progress
100.0%
Drone-monitored
Financial Progress
100.0%
Of awarded cost
Awarded Cost
₹1834 Cr
Contract value
Length
82.08 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
6623
Aerial captures
Stage
CC Issued & O&M by Construction Agency
Due Date
25-11-2013
Likely Date
30-06-2026
100.0%
Physical Done
Awarded
30-05-2011
Construction Started
30-05-2011
In Progress
Near Completion
29-06-2015
Completed
30-06-2026
UPC
N/09073/01001/BR
National Highway
77
Regional Office
RO-Patna
State
Bihar
Mode
BOT Annuity
Length
82.08 km
Contractor
BSC - C&C (JV)
Project Stage
CC Issued & O&M by Construction Agency
Drone Frames
6623 frames
Last Flight
2025-08-23
Awarded Cost
₹1834.00 Cr
Capital Cost
₹2290.72 Cr
Start Date
30-05-2011
PCOD Date
29-06-2015
Scheduled Completion
25-11-2013
Likely Completion
30-06-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 17:44:26
BSC - C&C (JV)
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 82.08 km on 77, improving regional connectivity.
6623 drone frames uploaded — real-time aerial monitoring is active for this project.
6,623 frames · NHAI surveillance footage · UPC N/09073/01001/BR