Rehabilitation and Upgradation of Chorma - Bairgania Section of National Highway No 227F to 2 lane with paved shoulders from Design Ch.0.000 to Ch. 34.566

UPC: N/07010/01001/BR

Physical Progress

100.0%

Drone-monitored

Financial Progress

100.0%

Of awarded cost

Awarded Cost

₹393 Cr

Contract value

Length

34.566 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

3307

Aerial captures

Project Progress

Physical Progress100.0%
Financial Progress100.0%

Stage

PCC Issued, CC Pending

Due Date

31-01-2026

Likely Date

30-09-2026

Completion

100.0%

Physical Done

DoneRemaining

Project Timeline

Awarded

01-02-2024

Construction Started

01-02-2024

In Progress

Near Completion

25-09-2025

Completed

30-09-2026

Physical vs Financial Progress

Project Details

UPC

N/07010/01001/BR

National Highway

227 F

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

34.566 km

Contractor

Dhariwal Buildtech Limited

Project Stage

PCC Issued, CC Pending

Drone Frames

3307 frames

Last Flight

2026-06-27

Cost & Timeline

Awarded Cost

₹393.11 Cr

Capital Cost

₹610.78 Cr

Start Date

01-02-2024

PCOD Date

25-09-2025

Scheduled Completion

31-01-2026

Likely Completion

30-09-2026

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-20 21:37:22

Contractor Profile

Dhariwal Buildtech Limited

RO-Patna227 FHAM

Project Intelligence

1

Construction is 100.0% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 34.566 km on 227 F, improving regional connectivity.

4

3307 drone frames uploaded — real-time aerial monitoring is active for this project.

Rehabilitation and Upgradation of Chorma - Bairgania Section of National Highway No 227F to 2 lane with paved shoulders from Design Ch.0.000 to Ch. 34.566 is a National Highways Authority of India (NHAI) project on 227 F in Bihar. The project has an awarded cost of ₹393.11 Cr and is currently ongoing with physical progress at 100.0%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

3,307 frames · NHAI surveillance footage · UPC N/07010/01001/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "Rehabilitation and Upgradation of Chorma - Bairgania Section of National Highwa"?
Current physical progress: 100.0%. Financial progress: 100.0%. Project stage: PCC Issued, CC Pending. On schedule. Scheduled completion: 31-01-2026. Likely completion: 30-09-2026.
QWho is the contractor for this NHAI highway project?
The contractor for Rehabilitation and Upgradation of Chorma - Bairgania Section of National Highway No 227F to 2 lane with paved shoulders from Design Ch.0.000 to Ch. 34.566 is Dhariwal Buildtech Limited. The project is under RO-Patna and covers 34.566 km on 227 F.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹393.11 Crore. Total capital cost: ₹610.78 Crore. The project is on 227 F in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/07010/01001/BR in NHAI?
UPC (Unique Project Code) N/07010/01001/BR refers to "Rehabilitation and Upgradation of Chorma - Bairgania Section of National Highway No 227F to 2 lane with paved shoulders from Design Ch.0.000 to Ch. 34.566 " — a National Highway project on 227 F in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.