All NHAI Projects
NH-319EPC 762 Drone Frames

Ara Bypass

UPC: N/05056/01004/BR

Physical Progress

25.8%

Drone-monitored

Financial Progress

4.3%

Of awarded cost

Awarded Cost

₹77 Cr

Contract value

Length

4.5 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

762

Aerial captures

Project Progress

Physical Progress25.8%
Financial Progress4.3%

Stage

Under Construction (AD issued)

Due Date

05-04-2027

Likely Date

05-04-2027

Completion

25.8%

Physical Done

DoneRemaining

Project Timeline

Awarded

06-10-2025

Construction Started

06-10-2025

In Progress

Near Completion

-

Completed

05-04-2027

Physical vs Financial Progress

Project Details

UPC

N/05056/01004/BR

National Highway

NH-319

Regional Office

RO-Patna

State

Bihar

Mode

EPC

Length

4.5 km

Contractor

Chandrawati Construction Pvt Ltd

Project Stage

Under Construction (AD issued)

Drone Frames

762 frames

Last Flight

2026-08-27

Cost & Timeline

Awarded Cost

₹76.69 Cr

Capital Cost

₹226.32 Cr

Start Date

06-10-2025

PCOD Date

-

Scheduled Completion

05-04-2027

Likely Completion

05-04-2027

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-13 18:29:51

Contractor Profile

Chandrawati Construction Pvt Ltd

RO-PatnaNH-319EPC

Project Intelligence

1

Physical progress stands at 25.8%. Financial utilization at 4.3%.

2

Project is on schedule or ahead of planned completion date.

3

Covers 4.5 km on NH-319, improving regional connectivity.

4

762 drone frames uploaded — real-time aerial monitoring is active for this project.

Ara Bypass is a National Highways Authority of India (NHAI) project on NH-319 in Bihar. The project has an awarded cost of ₹76.69 Cr and is currently ongoing with physical progress at 25.8%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

762 frames · NHAI surveillance footage · UPC N/05056/01004/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "Ara Bypass"?
Current physical progress: 25.8%. Financial progress: 4.3%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 05-04-2027. Likely completion: 05-04-2027.
QWho is the contractor for this NHAI highway project?
The contractor for Ara Bypass is Chandrawati Construction Pvt Ltd. The project is under RO-Patna and covers 4.5 km on NH-319.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹76.69 Crore. Total capital cost: ₹226.32 Crore. The project is on NH-319 in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/05056/01004/BR in NHAI?
UPC (Unique Project Code) N/05056/01004/BR refers to "Ara Bypass" — a National Highway project on NH-319 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.