NH-31EPC 1403 Drone Frames

Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 143.200 to Km. 159.255 (Pkg-1)

UPC: N/08055/02004/BR

Physical Progress

77.3%

Drone-monitored

Financial Progress

76.5%

Of awarded cost

Awarded Cost

₹303 Cr

Contract value

Length

16.05 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

1403

Aerial captures

Project Progress

Physical Progress77.3%
Financial Progress76.5%

Stage

Under Construction (AD issued)

Due Date

29-08-2026

Likely Date

28-10-2026

Completion

77.3%

Physical Done

DoneRemaining

Project Timeline

Awarded

30-08-2024

Construction Started

30-08-2024

In Progress

Near Completion

-

Completed

28-10-2026

Physical vs Financial Progress

Project Details

UPC

N/08055/02004/BR

National Highway

NH-31

Regional Office

RO-Patna

State

Bihar

Mode

EPC

Length

16.05 km

Contractor

R K Jain Projects Private Limited

Project Stage

Under Construction (AD issued)

Drone Frames

1403 frames

Last Flight

2026-08-27

Cost & Timeline

Awarded Cost

₹303.00 Cr

Capital Cost

₹470.50 Cr

Start Date

30-08-2024

PCOD Date

-

Scheduled Completion

29-08-2026

Likely Completion

28-10-2026

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-13 15:52:59

Contractor Profile

R K Jain Projects Private Limited

RO-PatnaNH-31EPC

Project Intelligence

1

Project is more than halfway complete at 77.3% physical progress.

2

Project is on schedule or ahead of planned completion date.

3

Covers 16.05 km on NH-31, improving regional connectivity.

4

1403 drone frames uploaded — real-time aerial monitoring is active for this project.

Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 143.200 to Km. 159.255 (Pkg-1) is a National Highways Authority of India (NHAI) project on NH-31 in Bihar. The project has an awarded cost of ₹303.00 Cr and is currently ongoing with physical progress at 77.3%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

1,403 frames · NHAI surveillance footage · UPC N/08055/02004/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 14"?
Current physical progress: 77.3%. Financial progress: 76.5%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 29-08-2026. Likely completion: 28-10-2026.
QWho is the contractor for this NHAI highway project?
The contractor for Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 143.200 to Km. 159.255 (Pkg-1) is R K Jain Projects Private Limited. The project is under RO-Patna and covers 16.05 km on NH-31.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹303.00 Crore. Total capital cost: ₹470.50 Crore. The project is on NH-31 in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/08055/02004/BR in NHAI?
UPC (Unique Project Code) N/08055/02004/BR refers to "Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 143.200 to Km. 159.255 (Pkg-1)" — a National Highway project on NH-31 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.