Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 143.200 to Km. 159.255 (Pkg-1)
Physical Progress
77.3%
Drone-monitored
Financial Progress
76.5%
Of awarded cost
Awarded Cost
₹303 Cr
Contract value
Length
16.05 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
1403
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
29-08-2026
Likely Date
28-10-2026
Completion
77.3%
Physical Done
Project Timeline
Awarded
30-08-2024
Construction Started
30-08-2024
In Progress
Near Completion
-
Completed
28-10-2026
Physical vs Financial Progress
Project Details
UPC
N/08055/02004/BR
National Highway
NH-31
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
16.05 km
Contractor
R K Jain Projects Private Limited
Project Stage
Under Construction (AD issued)
Drone Frames
1403 frames
Last Flight
2026-08-27
Cost & Timeline
Awarded Cost
₹303.00 Cr
Capital Cost
₹470.50 Cr
Start Date
30-08-2024
PCOD Date
-
Scheduled Completion
29-08-2026
Likely Completion
28-10-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-09-13 15:52:59
Contractor Profile
R K Jain Projects Private Limited
Project Intelligence
Project is more than halfway complete at 77.3% physical progress.
Project is on schedule or ahead of planned completion date.
Covers 16.05 km on NH-31, improving regional connectivity.
1403 drone frames uploaded — real-time aerial monitoring is active for this project.
Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 143.200 to Km. 159.255 (Pkg-1) is a National Highways Authority of India (NHAI) project on NH-31 in Bihar. The project has an awarded cost of ₹303.00 Cr and is currently ongoing with physical progress at 77.3%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
1,403 frames · NHAI surveillance footage · UPC N/08055/02004/BR
Frequently Asked Questions
- QWhat is the current status of the NHAI project "Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 14"?
- Current physical progress: 77.3%. Financial progress: 76.5%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 29-08-2026. Likely completion: 28-10-2026.
- QWho is the contractor for this NHAI highway project?
- The contractor for Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 143.200 to Km. 159.255 (Pkg-1) is R K Jain Projects Private Limited. The project is under RO-Patna and covers 16.05 km on NH-31.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹303.00 Crore. Total capital cost: ₹470.50 Crore. The project is on NH-31 in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/08055/02004/BR in NHAI?
- UPC (Unique Project Code) N/08055/02004/BR refers to "Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 143.200 to Km. 159.255 (Pkg-1)" — a National Highway project on NH-31 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.