All NHAI Projects
NH-80 (new NH-33)HAM

4 Laning of Green field Alignment of NH-33 (Old NH-80) (Mokama to Munger) in the state of Bihar.

UPC: N/08038/01004/BR

Physical Progress

0.0%

Drone-monitored

Financial Progress

0.0%

Of awarded cost

Awarded Cost

₹2441 Cr

Contract value

Length

82.4 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

N/A

Aerial captures

Project Progress

Physical Progress0.0%
Financial Progress0.0%

Stage

Awarded, Not Appointed

Due Date

-

Likely Date

-

Completion

0.0%

Physical Done

DoneRemaining

Project Timeline

Awarded

Appointed Date Pending

Construction Started

Appointed Date Pending

In Progress

Near Completion

-

Completed

-

Physical vs Financial Progress

Project Details

UPC

N/08038/01004/BR

National Highway

NH-80 (new NH-33)

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

82.4 km

Contractor

G R Infraprojects Limited

Project Stage

Awarded, Not Appointed

Drone Frames

N/A

Last Flight

N/A

Cost & Timeline

Awarded Cost

₹2440.87 Cr

Capital Cost

₹4447.38 Cr

Start Date

Appointed Date Pending

PCOD Date

-

Scheduled Completion

-

Likely Completion

-

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-20 21:44:52

Contractor Profile

G R Infraprojects Limited

RO-PatnaNH-80 (new NH-33)HAM

Project Intelligence

1

This is a mega infrastructure project worth ₹2441 Cr — among the largest NHAI projects in the region.

2

Physical progress stands at 0.0%. Financial utilization at 0.0%.

3

Project is on schedule or ahead of planned completion date.

4

Covers 82.4 km on NH-80 (new NH-33), improving regional connectivity.

4 Laning of Green field Alignment of NH-33 (Old NH-80) (Mokama to Munger) in the state of Bihar. is a National Highways Authority of India (NHAI) project on NH-80 (new NH-33) in Bihar. The project has an awarded cost of ₹2440.87 Cr and is currently ongoing with physical progress at 0.0%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

?

Frequently Asked Questions

QWhat is the current status of the NHAI project "4 Laning of Green field Alignment of NH-33 (Old NH-80) (Mokama to Munger) in the"?
Current physical progress: 0.0%. Financial progress: 0.0%. Project stage: Awarded, Not Appointed. On schedule. Scheduled completion: -. Likely completion: -.
QWho is the contractor for this NHAI highway project?
The contractor for 4 Laning of Green field Alignment of NH-33 (Old NH-80) (Mokama to Munger) in the state of Bihar. is G R Infraprojects Limited. The project is under RO-Patna and covers 82.4 km on NH-80 (new NH-33).
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹2440.87 Crore. Total capital cost: ₹4447.38 Crore. The project is on NH-80 (new NH-33) in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/08038/01004/BR in NHAI?
UPC (Unique Project Code) N/08038/01004/BR refers to "4 Laning of Green field Alignment of NH-33 (Old NH-80) (Mokama to Munger) in the state of Bihar." — a National Highway project on NH-80 (new NH-33) in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.