Original Cost
₹298 Cr
Baseline estimate
Revised Cost
₹298 Cr
Latest approved cost
Expenditure
₹235 Cr
Spent to date
Utilization
78.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹63 Cr
Budget left
Spent
₹235 Cr
Remaining
₹63 Cr
Total
₹298 Cr
Project Approved
Construction / Implementation
Original End Date
20/02/2019
Revised Completion
31/03/2026
Completed
Project is within original budget of ₹298 Cr — no cost escalation recorded.
Expenditure stands at ₹235 Cr, which is 78.8% of the revised project cost.
Remaining budget: ₹63 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.