Original Cost
₹411 Cr
Baseline estimate
Revised Cost
₹411 Cr
Latest approved cost
Expenditure
₹342 Cr
Spent to date
Utilization
83.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹69 Cr
Budget left
Spent
₹342 Cr
Remaining
₹69 Cr
Total
₹411 Cr
Project Approved
Construction / Implementation
Original End Date
12/05/2024
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹411 Cr — no cost escalation recorded.
Expenditure stands at ₹342 Cr, which is 83.2% of the revised project cost.
Remaining budget: ₹69 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.