Original Cost
₹1405 Cr
Baseline estimate
Revised Cost
₹1405 Cr
Latest approved cost
Expenditure
₹118 Cr
Spent to date
Utilization
8.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1287 Cr
Budget left
Spent
₹118 Cr
Remaining
₹1287 Cr
Total
₹1405 Cr
Project Approved
Construction / Implementation
Original End Date
08/05/2027
Revised Completion
Completed
Project is within original budget of ₹1405 Cr — no cost escalation recorded.
Expenditure stands at ₹118 Cr, which is 8.4% of the revised project cost.
Remaining budget: ₹1287 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.