Original Cost
₹1430 Cr
Baseline estimate
Revised Cost
₹1430 Cr
Latest approved cost
Expenditure
₹582 Cr
Spent to date
Utilization
40.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹848 Cr
Budget left
Spent
₹582 Cr
Remaining
₹848 Cr
Total
₹1430 Cr
Project Approved
Construction / Implementation
Original End Date
30/12/2026
Revised Completion
31/12/2027
Completed
Project is within original budget of ₹1430 Cr — no cost escalation recorded.
Expenditure stands at ₹582 Cr, which is 40.7% of the revised project cost.
Remaining budget: ₹848 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.