Original Cost
₹1876 Cr
Baseline estimate
Revised Cost
₹1876 Cr
Latest approved cost
Expenditure
₹614 Cr
Spent to date
Utilization
32.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1262 Cr
Budget left
Spent
₹614 Cr
Remaining
₹1262 Cr
Total
₹1876 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2019
Revised Completion
31/12/2027
Completed
Project is within original budget of ₹1876 Cr — no cost escalation recorded.
Expenditure stands at ₹614 Cr, which is 32.7% of the revised project cost.
Remaining budget: ₹1262 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.