Original Cost
₹2798 Cr
Baseline estimate
Revised Cost
₹2798 Cr
Latest approved cost
Expenditure
₹2569 Cr
Spent to date
Utilization
91.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹229 Cr
Budget left
Spent
₹2569 Cr
Remaining
₹229 Cr
Total
₹2798 Cr
Project Approved
Construction / Implementation
Original End Date
31/07/2030
Revised Completion
31/07/2030
Completed
Project is within original budget of ₹2798 Cr — no cost escalation recorded.
Expenditure stands at ₹2569 Cr, which is 91.8% of the revised project cost.
Remaining budget: ₹229 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.