STP at Hajipur
Original Cost
₹305 Cr
Baseline estimate
Revised Cost
₹305 Cr
Latest approved cost
Expenditure
₹346 Cr
Spent to date
Utilization
113.6%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹0 Cr
Budget left
Spent
₹346 Cr
Remaining
₹0 Cr
Total
₹305 Cr
113.6%
Utilized
Project Approved
Construction / Implementation
Original End Date
2025-06-30
Revised Completion
2025-12-31
Completed
Project is within original budget of ₹305 Cr — no cost escalation recorded.
Expenditure stands at ₹346 Cr, which is 113.6% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Waste & Water. Ministry: Department of Water Resources, River Development & GR.