Sewer Network, SPS and STP at Begusarai
Original Cost
₹230 Cr
Baseline estimate
Revised Cost
₹230 Cr
Latest approved cost
Expenditure
₹262 Cr
Spent to date
Utilization
113.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹0 Cr
Budget left
Budget Utilization
113.8%Spent
₹262 Cr
Remaining
₹0 Cr
Total
₹230 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/04/2025
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹230 Cr — no cost escalation recorded.
Expenditure stands at ₹262 Cr, which is 113.8% of the revised project cost.
Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Waste & Water. Ministry: Department of Water Resources, River Development & GR.
Sewer Network, SPS and STP at Begusarai is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Waste & Water sector. The original approved cost is ₹230.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Sewer Network, SPS and STP at Begusarai"?
- Sewer Network, SPS and STP at Begusarai is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Waste & Water. State: Bihar. Original cost: ₹230 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹230 Cr has not been significantly revised. Expenditure: ₹262 Cr (113.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Sewer Network, SPS and STP at Begusarai is under the Department of Water Resources, River Development & GR in the Waste & Water sector. Project code: 616615. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Sewer Network, SPS and STP at Begusarai is one of several Bihar projects tracked under the Waste & Water sector on the IPM system.