Original Cost
₹304 Cr
Baseline estimate
Revised Cost
₹304 Cr
Latest approved cost
Expenditure
₹85 Cr
Spent to date
Utilization
27.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹219 Cr
Budget left
Spent
₹85 Cr
Remaining
₹219 Cr
Total
₹304 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2026
Revised Completion
27/05/2027
Completed
Project is within original budget of ₹304 Cr — no cost escalation recorded.
Expenditure stands at ₹85 Cr, which is 27.8% of the revised project cost.
Remaining budget: ₹219 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.