Original Cost
₹350 Cr
Baseline estimate
Revised Cost
₹350 Cr
Latest approved cost
Expenditure
₹80 Cr
Spent to date
Utilization
23.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹269 Cr
Budget left
Spent
₹80 Cr
Remaining
₹269 Cr
Total
₹350 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2030
Revised Completion
30/03/2030
Completed
Project is within original budget of ₹350 Cr — no cost escalation recorded.
Expenditure stands at ₹80 Cr, which is 23.0% of the revised project cost.
Remaining budget: ₹269 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.