Project
Original Cost
₹519 Cr
Baseline estimate
Revised Cost
₹519 Cr
Latest approved cost
Expenditure
₹402 Cr
Spent to date
Utilization
77.4%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹117 Cr
Budget left
Spent
₹402 Cr
Remaining
₹117 Cr
Total
₹519 Cr
77.4%
Utilized
Project Approved
Construction / Implementation
Original End Date
2025-03-31
Revised Completion
2025-10-31
Completed
Project is within original budget of ₹519 Cr — no cost escalation recorded.
Expenditure stands at ₹402 Cr, which is 77.4% of the revised project cost.
Remaining budget: ₹117 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.