Asthan] New Railway line
Original Cost
₹735 Cr
Baseline estimate
Revised Cost
₹735 Cr
Latest approved cost
Expenditure
₹589 Cr
Spent to date
Utilization
80.2%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹146 Cr
Budget left
Spent
₹589 Cr
Remaining
₹146 Cr
Total
₹735 Cr
80.2%
Utilized
Project Approved
Construction / Implementation
Original End Date
2024-12-31
Revised Completion
2027-03-31
Completed
Project is within original budget of ₹735 Cr — no cost escalation recorded.
Expenditure stands at ₹589 Cr, which is 80.2% of the revised project cost.
Remaining budget: ₹146 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.