Original Cost
₹462 Cr
Baseline estimate
Revised Cost
₹462 Cr
Latest approved cost
Expenditure
₹239 Cr
Spent to date
Utilization
51.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹223 Cr
Budget left
Spent
₹239 Cr
Remaining
₹223 Cr
Total
₹462 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2027
Revised Completion
27/03/2027
Completed
Project is within original budget of ₹462 Cr — no cost escalation recorded.
Expenditure stands at ₹239 Cr, which is 51.8% of the revised project cost.
Remaining budget: ₹223 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.