SAAP-3 Water Supply Infrastructure SAAP-3 Project
Original Cost
₹159 Cr
Baseline estimate
Revised Cost
₹159 Cr
Latest approved cost
Expenditure
₹88 Cr
Spent to date
Utilization
55.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹72 Cr
Budget left
Budget Utilization
55.0%Spent
₹88 Cr
Remaining
₹72 Cr
Total
₹159 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/10/2023
Revised Completion
30/06/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹159 Cr — no cost escalation recorded.
Expenditure stands at ₹88 Cr, which is 55.0% of the revised project cost.
Remaining budget: ₹72 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Waste & Water. Ministry: Ministry of Housing & Urban Affairs.
SAAP-3 Water Supply Infrastructure SAAP-3 Project is a centrally-funded infrastructure project under Ministry of Housing & Urban Affairs, in the Waste & Water sector. The original approved cost is ₹159.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "SAAP-3 Water Supply Infrastructure SAAP-3 Project"?
- SAAP-3 Water Supply Infrastructure SAAP-3 Project is a centrally-funded infrastructure project under the Ministry of Housing & Urban Affairs, tracked through the Investment Project Monitoring (IPM) system. Sector: Waste & Water. State: Jharkhand. Original cost: ₹159 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹159 Cr has not been significantly revised. Expenditure: ₹88 Cr (55.0% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- SAAP-3 Water Supply Infrastructure SAAP-3 Project is under the Ministry of Housing & Urban Affairs in the Waste & Water sector. Project code: 702742. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. SAAP-3 Water Supply Infrastructure SAAP-3 Project is one of several Bihar projects tracked under the Waste & Water sector on the IPM system.