2 lane with paved shoulders from Design Ch.0.000 to Ch. 34.566
Original Cost
₹611 Cr
Baseline estimate
Revised Cost
₹629 Cr
Latest approved cost
Expenditure
₹329 Cr
Spent to date
Utilization
52.3%
Of revised cost
Cost Overrun
+2.9%
+₹18 Cr
Remaining
₹300 Cr
Budget left
Spent
₹329 Cr
Remaining
₹300 Cr
Total
₹629 Cr
52.3%
Utilized
Original Cost
₹611 Cr
Revised Cost
₹629 Cr
Increase
+₹18 Cr
Escalation
+2.9%
Project Approved
Construction / Implementation
Original End Date
2026-01-31
Revised Completion
2026-05-15
Completed
Cost has increased by ₹18 Cr (2.9%) from the original estimate of ₹611 Cr.
Expenditure stands at ₹329 Cr, which is 52.3% of the revised project cost.
Remaining budget: ₹300 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.