Original Cost
₹611 Cr
Baseline estimate
Revised Cost
₹629 Cr
Latest approved cost
Expenditure
₹335 Cr
Spent to date
Utilization
53.3%
Of revised budget
Cost Status
+2.9%
+₹18 Cr increase
Remaining
₹294 Cr
Budget left
Spent
₹335 Cr
Remaining
₹294 Cr
Total
₹629 Cr
Original Cost
₹611 Cr
Revised Cost
₹629 Cr
Increase
+₹18 Cr
Escalation
+2.9%
Project Approved
Construction / Implementation
Original End Date
31/01/2026
Revised Completion
30/06/2026
Completed
Cost has increased by ₹18 Cr (2.9%) from the original estimate of ₹611 Cr.
Expenditure stands at ₹335 Cr, which is 53.3% of the revised project cost.
Remaining budget: ₹294 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.