Original Cost
₹303 Cr
Baseline estimate
Revised Cost
₹303 Cr
Latest approved cost
Expenditure
₹183 Cr
Spent to date
Utilization
60.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹120 Cr
Budget left
Spent
₹183 Cr
Remaining
₹120 Cr
Total
₹303 Cr
Project Approved
Construction / Implementation
Original End Date
10/08/2023
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹303 Cr — no cost escalation recorded.
Expenditure stands at ₹183 Cr, which is 60.3% of the revised project cost.
Remaining budget: ₹120 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.