Original Cost
₹32.9K Cr
Baseline estimate
Revised Cost
₹32.8K Cr
Latest approved cost
Expenditure
₹14.4K Cr
Spent to date
Utilization
43.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹18.5K Cr
Budget left
Spent
₹14.4K Cr
Remaining
₹18.5K Cr
Total
₹32.8K Cr
Project Approved
Construction / Implementation
Original End Date
31/12/2025
Revised Completion
31/12/2025
Completed
Mega infrastructure project worth ₹32.8K Cr — among the largest central projects in Delhi.
Project is within original budget of ₹32.9K Cr — no cost escalation recorded.
Expenditure stands at ₹14.4K Cr, which is 43.8% of the revised project cost.
Remaining budget: ₹18.5K Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Real Estate. Ministry: Ministry of Housing & Urban Affairs.