Original Cost
₹1656 Cr
Baseline estimate
Revised Cost
₹6500 Cr
Latest approved cost
Expenditure
₹4607 Cr
Spent to date
Utilization
70.9%
Of revised budget
Cost Status
+292.5%
+₹4844 Cr increase
Remaining
₹1893 Cr
Budget left
Spent
₹4607 Cr
Remaining
₹1893 Cr
Total
₹6500 Cr
Original Cost
₹1656 Cr
Revised Cost
₹6500 Cr
Increase
+₹4844 Cr
Escalation
+292.5%
Project Approved
Construction / Implementation
Original End Date
31/03/2027
Revised Completion
30/09/2028
Completed
Cost has increased by ₹4844 Cr (292.5%) from the original estimate of ₹1656 Cr.
Expenditure stands at ₹4607 Cr, which is 70.9% of the revised project cost.
Remaining budget: ₹1893 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.