Railway Line Doubling
Original Cost
₹2374 Cr
Baseline estimate
Revised Cost
₹1700 Cr
Latest approved cost
Expenditure
₹1610 Cr
Spent to date
Utilization
94.7%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹90 Cr
Budget left
Spent
₹1610 Cr
Remaining
₹90 Cr
Total
₹1700 Cr
94.7%
Utilized
Project Approved
Construction / Implementation
Original End Date
2024-12-01
Revised Completion
2025-12-31
Completed
Project is within original budget of ₹2374 Cr — no cost escalation recorded.
Expenditure stands at ₹1610 Cr, which is 94.7% of the revised project cost.
Remaining budget: ₹90 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.