Original Cost
₹3032 Cr
Baseline estimate
Revised Cost
₹5073 Cr
Latest approved cost
Expenditure
₹4171 Cr
Spent to date
Utilization
82.2%
Of revised budget
Cost Status
+67.3%
+₹2041 Cr increase
Remaining
₹902 Cr
Budget left
Spent
₹4171 Cr
Remaining
₹902 Cr
Total
₹5073 Cr
Original Cost
₹3032 Cr
Revised Cost
₹5073 Cr
Increase
+₹2041 Cr
Escalation
+67.3%
Project Approved
Construction / Implementation
Original End Date
25/12/2025
Revised Completion
31/12/2027
Completed
Cost has increased by ₹2041 Cr (67.3%) from the original estimate of ₹3032 Cr.
Expenditure stands at ₹4171 Cr, which is 82.2% of the revised project cost.
Remaining budget: ₹902 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.